chore(agent workflows): remove GitHub Projects integration

This commit is contained in:
Tommaso Casaburi
2026-07-21 16:43:35 +07:00
parent 18a1c096d1
commit 9a1f35fc67
6 changed files with 3 additions and 126 deletions

View File

@@ -149,32 +149,7 @@ If the user later explicitly asks to merge after reviews pass, a separate merge
gh pr merge --squash --delete-branch
```
### 9. Add to project board
Use **gh CLI** for project operations (never GitHub MCP).
Add the issue to the project when the PR is opened, but do **not** force it to `Done` yet.
```bash
ITEM_JSON=$(gh project item-add 1 --owner bitsocialnet --url "https://github.com/bitsocialnet/seedit/issues/ISSUE_NUMBER" --format json)
ITEM_ID=$(echo "$ITEM_JSON" | jq -r '.id')
```
If the user later explicitly asks to merge the reviewed PR in the same run, reuse `ITEM_ID` and then set the project item to `Done`:
```bash
# Get Status field ID and Done option ID from project
FIELD_JSON=$(gh project field-list 1 --owner bitsocialnet --format json)
STATUS_FIELD_ID=$(echo "$FIELD_JSON" | jq -r '.fields[] | select(.name=="Status") | .id')
DONE_OPTION_ID=$(echo "$FIELD_JSON" | jq -r '.fields[] | select(.name=="Status") | .options[] | select(.name=="Done") | .id')
# Set status to Done
gh project item-edit --id "$ITEM_ID" --project-id PVT_kwDODohK7M4BM4wg --field-id "$STATUS_FIELD_ID" --single-select-option-id "$DONE_OPTION_ID"
```
Assignees and labels are inherited from the issue (set in step 6) — no separate project update needed.
### 10. Report summary
### 9. Report summary
Print a summary to the user:
@@ -184,7 +159,6 @@ Issue #NUMBER created, committed, pushed, and linked to a PR into master.
Commit: HASH
Labels: label1, label2
PR: PR_URL
Project: seedit
URL: https://github.com/bitsocialnet/seedit/issues/NUMBER
```

View File

@@ -127,8 +127,6 @@ For every linked issue, bring it into the same final state expected from `make-c
- closed
- assigned to the current GitHub user
- added to the `seedit` project if missing
- project status `Done`
Before editing issue assignees, determine the current contributor's GitHub username from the authenticated `gh` session.
If `gh` is not signed in or cannot resolve the login, stop and ask the contributor for their GitHub username before proceeding.
@@ -147,10 +145,6 @@ fi
ISSUE_NUMBERS=$(gh pr view <pr-number> --repo bitsocialnet/seedit --json closingIssuesReferences --jq '.closingIssuesReferences[].number')
if [ -n "$ISSUE_NUMBERS" ]; then
FIELD_JSON=$(gh project field-list 1 --owner bitsocialnet --format json)
STATUS_FIELD_ID=$(echo "$FIELD_JSON" | jq -r '.fields[] | select(.name=="Status") | .id')
DONE_OPTION_ID=$(echo "$FIELD_JSON" | jq -r '.fields[] | select(.name=="Status") | .options[] | select(.name=="Done") | .id')
for ISSUE_NUMBER in $ISSUE_NUMBERS; do
ISSUE_STATE=$(gh issue view "$ISSUE_NUMBER" --repo bitsocialnet/seedit --json state --jq '.state')
if [ "$ISSUE_STATE" != "CLOSED" ]; then
@@ -160,14 +154,6 @@ if [ -n "$ISSUE_NUMBERS" ]; then
if ! gh issue view "$ISSUE_NUMBER" --repo bitsocialnet/seedit --json assignees --jq '.assignees[].login' | grep -qx "$GH_LOGIN"; then
gh issue edit "$ISSUE_NUMBER" --repo bitsocialnet/seedit --add-assignee "$GH_LOGIN"
fi
ITEM_ID=$(gh project item-list 1 --owner bitsocialnet --limit 1000 --format json --jq ".items[] | select(.content.number == $ISSUE_NUMBER) | .id" | head -n1)
if [ -z "$ITEM_ID" ]; then
ITEM_JSON=$(gh project item-add 1 --owner bitsocialnet --url "https://github.com/bitsocialnet/seedit/issues/$ISSUE_NUMBER" --format json)
ITEM_ID=$(echo "$ITEM_JSON" | jq -r '.id')
fi
gh project item-edit --id "$ITEM_ID" --project-id PVT_kwDODohK7M4BM4wg --field-id "$STATUS_FIELD_ID" --single-select-option-id "$DONE_OPTION_ID"
done
fi
```
@@ -206,6 +192,5 @@ Tell the user:
- whether the PR was merged
- whether linked issues were confirmed closed
- whether linked issues were assigned to the current GitHub user
- whether linked project items were confirmed `Done`
- whether stale remote-tracking refs were pruned
- whether the feature branch, local `pr/<number>` alias, and any worktree were cleaned up

View File

@@ -149,32 +149,7 @@ If the user later explicitly asks to merge after reviews pass, a separate merge
gh pr merge --squash --delete-branch
```
### 9. Add to project board
Use **gh CLI** for project operations (never GitHub MCP).
Add the issue to the project when the PR is opened, but do **not** force it to `Done` yet.
```bash
ITEM_JSON=$(gh project item-add 1 --owner bitsocialnet --url "https://github.com/bitsocialnet/seedit/issues/ISSUE_NUMBER" --format json)
ITEM_ID=$(echo "$ITEM_JSON" | jq -r '.id')
```
If the user later explicitly asks to merge the reviewed PR in the same run, reuse `ITEM_ID` and then set the project item to `Done`:
```bash
# Get Status field ID and Done option ID from project
FIELD_JSON=$(gh project field-list 1 --owner bitsocialnet --format json)
STATUS_FIELD_ID=$(echo "$FIELD_JSON" | jq -r '.fields[] | select(.name=="Status") | .id')
DONE_OPTION_ID=$(echo "$FIELD_JSON" | jq -r '.fields[] | select(.name=="Status") | .options[] | select(.name=="Done") | .id')
# Set status to Done
gh project item-edit --id "$ITEM_ID" --project-id PVT_kwDODohK7M4BM4wg --field-id "$STATUS_FIELD_ID" --single-select-option-id "$DONE_OPTION_ID"
```
Assignees and labels are inherited from the issue (set in step 6) — no separate project update needed.
### 10. Report summary
### 9. Report summary
Print a summary to the user:
@@ -184,7 +159,6 @@ Issue #NUMBER created, committed, pushed, and linked to a PR into master.
Commit: HASH
Labels: label1, label2
PR: PR_URL
Project: seedit
URL: https://github.com/bitsocialnet/seedit/issues/NUMBER
```

View File

@@ -127,8 +127,6 @@ For every linked issue, bring it into the same final state expected from `make-c
- closed
- assigned to the current GitHub user
- added to the `seedit` project if missing
- project status `Done`
Before editing issue assignees, determine the current contributor's GitHub username from the authenticated `gh` session.
If `gh` is not signed in or cannot resolve the login, stop and ask the contributor for their GitHub username before proceeding.
@@ -147,10 +145,6 @@ fi
ISSUE_NUMBERS=$(gh pr view <pr-number> --repo bitsocialnet/seedit --json closingIssuesReferences --jq '.closingIssuesReferences[].number')
if [ -n "$ISSUE_NUMBERS" ]; then
FIELD_JSON=$(gh project field-list 1 --owner bitsocialnet --format json)
STATUS_FIELD_ID=$(echo "$FIELD_JSON" | jq -r '.fields[] | select(.name=="Status") | .id')
DONE_OPTION_ID=$(echo "$FIELD_JSON" | jq -r '.fields[] | select(.name=="Status") | .options[] | select(.name=="Done") | .id')
for ISSUE_NUMBER in $ISSUE_NUMBERS; do
ISSUE_STATE=$(gh issue view "$ISSUE_NUMBER" --repo bitsocialnet/seedit --json state --jq '.state')
if [ "$ISSUE_STATE" != "CLOSED" ]; then
@@ -160,14 +154,6 @@ if [ -n "$ISSUE_NUMBERS" ]; then
if ! gh issue view "$ISSUE_NUMBER" --repo bitsocialnet/seedit --json assignees --jq '.assignees[].login' | grep -qx "$GH_LOGIN"; then
gh issue edit "$ISSUE_NUMBER" --repo bitsocialnet/seedit --add-assignee "$GH_LOGIN"
fi
ITEM_ID=$(gh project item-list 1 --owner bitsocialnet --limit 1000 --format json --jq ".items[] | select(.content.number == $ISSUE_NUMBER) | .id" | head -n1)
if [ -z "$ITEM_ID" ]; then
ITEM_JSON=$(gh project item-add 1 --owner bitsocialnet --url "https://github.com/bitsocialnet/seedit/issues/$ISSUE_NUMBER" --format json)
ITEM_ID=$(echo "$ITEM_JSON" | jq -r '.id')
fi
gh project item-edit --id "$ITEM_ID" --project-id PVT_kwDODohK7M4BM4wg --field-id "$STATUS_FIELD_ID" --single-select-option-id "$DONE_OPTION_ID"
done
fi
```
@@ -206,6 +192,5 @@ Tell the user:
- whether the PR was merged
- whether linked issues were confirmed closed
- whether linked issues were assigned to the current GitHub user
- whether linked project items were confirmed `Done`
- whether stale remote-tracking refs were pruned
- whether the feature branch, local `pr/<number>` alias, and any worktree were cleaned up

View File

@@ -149,32 +149,7 @@ If the user later explicitly asks to merge after reviews pass, a separate merge
gh pr merge --squash --delete-branch
```
### 9. Add to project board
Use **gh CLI** for project operations (never GitHub MCP).
Add the issue to the project when the PR is opened, but do **not** force it to `Done` yet.
```bash
ITEM_JSON=$(gh project item-add 1 --owner bitsocialnet --url "https://github.com/bitsocialnet/seedit/issues/ISSUE_NUMBER" --format json)
ITEM_ID=$(echo "$ITEM_JSON" | jq -r '.id')
```
If the user later explicitly asks to merge the reviewed PR in the same run, reuse `ITEM_ID` and then set the project item to `Done`:
```bash
# Get Status field ID and Done option ID from project
FIELD_JSON=$(gh project field-list 1 --owner bitsocialnet --format json)
STATUS_FIELD_ID=$(echo "$FIELD_JSON" | jq -r '.fields[] | select(.name=="Status") | .id')
DONE_OPTION_ID=$(echo "$FIELD_JSON" | jq -r '.fields[] | select(.name=="Status") | .options[] | select(.name=="Done") | .id')
# Set status to Done
gh project item-edit --id "$ITEM_ID" --project-id PVT_kwDODohK7M4BM4wg --field-id "$STATUS_FIELD_ID" --single-select-option-id "$DONE_OPTION_ID"
```
Assignees and labels are inherited from the issue (set in step 6) — no separate project update needed.
### 10. Report summary
### 9. Report summary
Print a summary to the user:
@@ -184,7 +159,6 @@ Issue #NUMBER created, committed, pushed, and linked to a PR into master.
Commit: HASH
Labels: label1, label2
PR: PR_URL
Project: seedit
URL: https://github.com/bitsocialnet/seedit/issues/NUMBER
```

View File

@@ -127,8 +127,6 @@ For every linked issue, bring it into the same final state expected from `make-c
- closed
- assigned to the current GitHub user
- added to the `seedit` project if missing
- project status `Done`
Before editing issue assignees, determine the current contributor's GitHub username from the authenticated `gh` session.
If `gh` is not signed in or cannot resolve the login, stop and ask the contributor for their GitHub username before proceeding.
@@ -147,10 +145,6 @@ fi
ISSUE_NUMBERS=$(gh pr view <pr-number> --repo bitsocialnet/seedit --json closingIssuesReferences --jq '.closingIssuesReferences[].number')
if [ -n "$ISSUE_NUMBERS" ]; then
FIELD_JSON=$(gh project field-list 1 --owner bitsocialnet --format json)
STATUS_FIELD_ID=$(echo "$FIELD_JSON" | jq -r '.fields[] | select(.name=="Status") | .id')
DONE_OPTION_ID=$(echo "$FIELD_JSON" | jq -r '.fields[] | select(.name=="Status") | .options[] | select(.name=="Done") | .id')
for ISSUE_NUMBER in $ISSUE_NUMBERS; do
ISSUE_STATE=$(gh issue view "$ISSUE_NUMBER" --repo bitsocialnet/seedit --json state --jq '.state')
if [ "$ISSUE_STATE" != "CLOSED" ]; then
@@ -160,14 +154,6 @@ if [ -n "$ISSUE_NUMBERS" ]; then
if ! gh issue view "$ISSUE_NUMBER" --repo bitsocialnet/seedit --json assignees --jq '.assignees[].login' | grep -qx "$GH_LOGIN"; then
gh issue edit "$ISSUE_NUMBER" --repo bitsocialnet/seedit --add-assignee "$GH_LOGIN"
fi
ITEM_ID=$(gh project item-list 1 --owner bitsocialnet --limit 1000 --format json --jq ".items[] | select(.content.number == $ISSUE_NUMBER) | .id" | head -n1)
if [ -z "$ITEM_ID" ]; then
ITEM_JSON=$(gh project item-add 1 --owner bitsocialnet --url "https://github.com/bitsocialnet/seedit/issues/$ISSUE_NUMBER" --format json)
ITEM_ID=$(echo "$ITEM_JSON" | jq -r '.id')
fi
gh project item-edit --id "$ITEM_ID" --project-id PVT_kwDODohK7M4BM4wg --field-id "$STATUS_FIELD_ID" --single-select-option-id "$DONE_OPTION_ID"
done
fi
```
@@ -206,6 +192,5 @@ Tell the user:
- whether the PR was merged
- whether linked issues were confirmed closed
- whether linked issues were assigned to the current GitHub user
- whether linked project items were confirmed `Done`
- whether stale remote-tracking refs were pruned
- whether the feature branch, local `pr/<number>` alias, and any worktree were cleaned up